Kettering - February 2021

Reinforced footings
Kettering - February 2021

Installation of all ground heave (underneath), rebar and beam form in this project for 25 houses in Kettering.

Baldock - January 2021

Crane base
Baldock - January 2021

Crane base and reinforced footings for a new retirement village in Baldock.

Dunstable - January 2021

Reinforced podium slab
Dunstable - January 2021

This 100 tonne podium slab was installed in Dunstable 1 week ahead of program.

Paris - November 2020

First base & large slabs
Paris - November 2020

Our first large overseas contract took us to Paris for multiple bases and a large RC slab installation

Rugby - October 2020

Steel, Pecavoid, and Peccafil
Rugby - October 2020

Installation of ground heave (pecavoid), ground beams (steel) and beam form (pecafill) around the sides on 30 houses in Rugby.

Harrow - October 2016

Crane base
Harrow - October 2016

This contract was initially for the construction of a crane base, which led onto steel and concrete for a full block of flats. The project ran from October 2016 to December 2016.

Clapham - September 2016

Basement
Clapham - September 2016

This project consisted of two large identical basements each with three homes built on top. We were contracted for full construction including Steel, shuttering and concrete. Completed between July 2016 and October 2016 for Titan Construction.

Radlett - June 2016

Basement
Radlett - June 2016

This project ran from March 2016 to July 2016. The contract was to construct the basement of a large detached house.